午夜精品电影,99re热精品视频,在线亚洲+欧美+日本专区,欧美第6页,中国黄色片视频,四虎成人永久,一区二区三区四区五区在线

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A seller is awarded a contract to build a pipeline. The contract terms and conditions require that a work plan be issued for the buyer's approval prior to commencing work, but the seller fails to provide one. Which of the following is the BEST thing for the buyer's project manager to do?
A、File a letter of intent.
B、Develop the work plan and issue it to the seller to move things along.
C、Issue a default letter.
D、Issue a stop work order to the seller until a work plan is prepared.


相關(guān)試題

推薦文章