當前位置:信管網 >> 在線考試中心 >> 信息系統項目管理師題庫 >> 試題查看
試卷名稱 2017年信息系統項目管理師最新英語模擬題(2)
考試中心《2017年信息系統項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

A project manager has been assigned to implement new server equipment into a data center. Through a risk workshop, the following two risks have been identified and assessed as highly likely to occur.1. Equipment is delayed due to shortages of key components.2. The customer has not initiated preparation of the data center, risking a delay in the project.What should the project manager do next?
A、Initiate the risk mitigation process
B、Conduct a Monte Carlo analysis
C、Add to the risk management plan
D、Initiate risk response planning