試題內(nèi)容

In all projects, needs must be tempered by schedule , cost and resource constraints. Project success depends primarily on ()。
 A. The quality of the  schedule  and cost control analysis
 B. Customer satistaction 
 C. Cuctomer compromise in defining its needs
 D. Exceeding customer requirements through gold-plating